| Hanover High School Project Update Leaching Field Project |
|
- Awarded to Case from North Attleboro for $206,900
- Work has been on-going with the new leaching field installed, and the new pump chamber in process of being installed.
- Work scheduled to be substantially complete by 8/15/09
Main Building Project: |
- 100% Construction Drawings completed by HMFH on 7/31/09
- 90% estimate performed by HMFH which still shows the project’s cost at $305.72/sf which meets the intent of the MSBA Project Funding Agreement
- Contractors and Filed Sub Contactors have been pre-qualified by the Selection Subcommittee pr Chapter 149 of the MGLs.
- Bid period starts 8/4/09, ends with filed sub contractors on 8/25/09 and general bids due 9/9/09
- Final building size is 157,000 sf and is estimated to costs approximately $46M
- Three alts are concession stand, turf field and maintenance building
- Construction slated to start no later than 10/1/09
- New High School substantial completion date is scheduled for 6/1/11 with move into the new school over the summer 2011 and the demo and associated site work to be completed no later than 6/1/2012
- Hanover has been receiving its 48.27% reimbursement from the MSBA for costs to date. The project is attempting to receive 2 additional points for MA-CHPs which would be realized at the end of the project and prorated back to the budget.
|
|
|